The Development Phase custom code and integrations development continued throughout this period. In addition updates were made to the Technical Design Document (TDD) to account for the Technology One SDK technical details.
The continuation of the Development phase has also involved the ongoing project management activities to manage risks and issues, communications, change requests and project plan updates. Change requests CR-02 for Microsoft Dynamics CRM 4.0 Update Rollup 1 and CR-03 for the integration options paper were submitted to and approved by BBSC.
The development of the Production environment specification was completed and reviewed with BBSC. This document enables BBSC to commence their procurement process for the required hardware and software components; as well as provides production environment knowledge transfer to BBSC IT. The document is currently being further reviewed by BBSC to validate the procurement options prior to confirmation and finalisation.
The development of the test scripts for process, integration and data acceptance testing is currently underway by BBSC for a target completion date of December 19th. In addition, the development of the training guides by BBSC should now have commenced based on the design documentation that was formally accepted by BBSC.